Concrete Calculator

Calculate how much concrete you need in cubic metres or bags for slabs, footings, posts and columns.

Source: GOV.UK — Building Regulations Approved Document A

Konstantin Iakovlev

By Konstantin Iakovlev · Founder, Calks.uk

Last updated: · Verified against UK building regulations 2026

Volume

0.90 m³

Weight

2.16 tonnes

25kg Bags

75

20kg Bags

90

Disclaimer

This calculator is for guidance only. Confirm quantities with your supplier before ordering, and use a qualified tradesperson for structural work. Rates and figures come from manufacturer coverage data and UK building regulations and are reviewed for 2026. Everything is calculated in your browser; nothing you enter is sent to our servers.

How It Works

Concrete volume is calculated by multiplying length × width × depth for rectangular slabs, or πr² × depth for circular areas such as post holes. The result in cubic metres tells you how much ready-mix to order, or how many bags of dry mix you need. A standard 25 kg bag of post-mix makes approximately 0.011 m³ of concrete. A slab of 5m × 3m × 0.10m therefore comes to 1.5 m³, while a shed base of 3 m × 2.4 m × 0.1 m works out at 0.72 m³, rising to 0.79 m³ once 10% wastage is added, which is roughly 72 bags.

For small jobs (under 1 m³), bagged dry-mix is practical. For larger pours, ready-mix delivery is more economical and gives consistent quality. Most UK suppliers sell ready-mix in minimum loads of 1 m³ for mini-mix and 6 m³ for standard trucks, although some firms will bring 0.5 m³ at a premium. Add 5-10% for wastage, spillage and uneven ground. Typical UK pricing in 2026 runs at £100-£140 per cubic metre delivered. Enter your dimensions and the calculator shows the volume in cubic metres, the number of 25 kg bags needed and an approximate cost estimate.

Mix ratios are quoted by volume as cement, sand and aggregate. C7.5, used for footpaths and light foundations, is 1:4:6. C20/25 for residential slabs and driveways is 1:2:4. C25/30 for structural work and beams is 1:1.5:3, and C30/40 for heavy industrial use is 1:1:2. A domestic driveway normally takes C25 at £110-£130 per cubic metre, while garage and shed foundations manage on C20 at £100-£115. For DIY mixing under 0.5 m³, bagged general purpose ballast, which is sand and aggregate already combined, at 1 part cement to 5 parts ballast is the simplest route.

Building Regulations set minimum depths that catch people out. Foundations should go at least 1m below ground level in clay soils because of heave risk, or 600mm in sandy and gravel soils. Trees change that picture. Within one tree height of a mature tree, 1.5m or more is recommended, and thirsty species such as oak and willow can demand 2.5m or more. Slab thickness has its own minimums, at 100mm for a domestic patio, 125mm for a driveway carrying cars, and 150mm or more for vans and heavy use. A142 mesh is standard reinforcement for driveways, with A193 where vehicles load the slab. Any structural foundation work needs a Building Notice or Full Plans, so speak to local Building Control first.

Concrete gains strength slowly rather than all at once. It reaches 70% of its strength at 7 days and 95% at 28 days, the industry standard for testing. Light foot traffic is fine after 24-48 hours, cars after 7 days, and full loading after 28 days. Curing conditions matter more than most people expect, with 10-25°C and 60-90% humidity being ideal. Below 5°C the concrete will not cure properly, so use an accelerator additive or wait for milder weather. Above 30°C it dries too fast and cracks, so mist the surface with water for the first 3 days. Covering the pour with plastic sheeting or wet hessian gives a slower, stronger cure, and in a UK winter it is worth avoiding any pour where the ground temperature is below 5°C.

Project costs put the concrete itself in perspective. A patio of 20 m² at 100mm needs 2 m³, so £220-£280 of ready-mix sits alongside £150 of base materials such as Type 1 sub-base and weed membrane, plus £500-£800 of labour if you hire it, giving £870-£1,230 in total. A driveway of 50 m² at 125mm takes £325-£420 of concrete, £400 of base, £150 of edging and £1,500-£2,500 of labour, so £2,400-£3,500 overall. A shed base of 3m × 2m at 100mm needs only 0.6 m³, and because the minimum ready-mix order would force you to buy a full cubic metre, roughly 40 bags at £6 each, about £240 plus 4 hours of work, often makes better sense.

Example: Garden shed base, 3 m × 2.4 m × 0.1 m deep

  1. Volume: 3 × 2.4 × 0.1 = 0.72 m³
  2. Add 10% wastage: 0.72 × 1.10 = 0.79 m³
  3. Bags (25 kg post-mix): 0.79 ÷ 0.011 ≈ 72 bags
  4. Or order 1 m³ ready-mix (typical minimum load)

Source: GOV.UK — Building Regulations Approved Document A

Frequently Asked Questions

How do I work out how much concrete a slab needs?
For a rectangular slab, multiply length by width by depth. For round post holes, use pi times the radius squared times depth. The result in cubic metres tells you how much ready-mix to order, and a 25 kg bag of post-mix makes about 0.011 cubic metres. Add 5-10% on top for wastage, spillage and uneven ground before you place the order.
Should I use bags or order ready-mix concrete?
Under 1 m³ the bags usually win, because the minimum ready-mix load is 1 m³ for mini-mix and 6 m³ for a standard truck, though some suppliers will deliver 0.5 m³ at a premium. Above that, ready-mix is both cheaper and more consistent, at roughly £100-£140 per cubic metre delivered in 2026. A shed base needing 0.6 m³ is the awkward case, since paying for a full cubic metre may cost more than about 40 bags at £6 and 4 hours of mixing.
Which concrete mix should I use for a driveway?
A domestic driveway normally takes C25, and the C20/25 grade covering residential slabs and driveways is mixed 1:2:4 by volume as cement, sand and aggregate, at around £110-£130 per cubic metre. Garage and shed foundations manage on C20 at £100-£115. Footpaths and light foundations only need C7.5 at 1:4:6, while structural work and beams call for C25/30 at 1:1.5:3 and heavy industrial slabs for C30/40 at 1:1:2. If you are mixing under 0.5 m³ yourself, bagged general purpose ballast at 1 part cement to 5 parts ballast is simplest.
How long does concrete take to cure properly?
Concrete reaches 70% of its strength at 7 days and 95% at 28 days, which is the point used for testing. You can walk on it after 24-48 hours, drive a car on it after 7 days, and load it fully after 28 days. Ideal conditions are 10-25°C with 60-90% humidity. Below 5°C it will not cure properly, so use an accelerator or wait, and above 30°C mist the surface with water for the first 3 days to stop it cracking.
Do I need mesh reinforcement in a concrete slab?
Slabs larger than 4m², or any slab that will carry weight, should have A142 or A193 steel mesh, around 1.5kg per square metre. A142 is the standard choice for driveways and A193 suits areas taking vehicle loads. Position the mesh a third of the way up from the bottom of the slab rather than resting it on the base. Keep the finished pour moist for 7 days or more under polythene or wet hessian while it hardens.