Concrete Calculator
Calculate how much concrete you need in cubic metres or bags for slabs, footings, posts and columns.
By Konstantin Iakovlev · Founder, Calks.uk
Last updated: · Depths checked against Approved Document A; prices from Checkatrade, August 2026
Volume
0.90 m³
With Wastage
0.99 m³
Weight
2.38 tonnes
25kg Bags
80
20kg Bags
99
Weight and bags include wastage. Bags assume about 0.01 m³ from a 20 kg bag (Wickes) and the same rate for 25 kg, so 0.0125 m³. Check the yield on the bag you buy.
Disclaimer
This calculator is for guidance only. Confirm quantities with your supplier before ordering, and use a qualified tradesperson for structural work. Rates and figures come from Approved Document A, Checkatrade and supplier data and are reviewed for 2026. Everything is calculated in your browser; nothing you enter is sent to our servers.
How It Works
Concrete volume is calculated by multiplying length × width × depth for rectangular slabs, or πr² × depth for circular areas such as post holes. The result in cubic metres tells you how much ready-mix to order, or how many bags of dry mix you need. Wickes says a 20 kg bag of ready-to-use concrete makes around 0.01 m³, and the calculator applies the same rate to a 25 kg bag, so 0.0125 m³. A slab of 5m × 3m × 0.10m therefore comes to 1.5 m³, while a shed base of 3 m × 2.4 m × 0.1 m works out at 0.72 m³, rising to 0.79 m³ once 10% wastage is added, which is 64 bags of 25 kg or 80 bags of 20 kg.
Bagged dry-mix is practical for small jobs such as post holes and small pads. For larger pours, ready-mix delivery is more economical and gives consistent quality. Checkatrade's guide, updated in August 2026, puts ready-mix at £100-£160 per cubic metre plus £100-£200 for delivery, averaging about £195 per cubic metre all in, with a minimum order of about £500 and a possible part-load fee below a full 6 m³ load. Add 5-10% for wastage, spillage and uneven ground, which you can set in the calculator. Enter your dimensions and the calculator shows the volume in cubic metres, the amount with wastage, the weight and the number of 25 kg and 20 kg bags needed.
Mix ratios are quoted by volume as cement, sand and aggregate, and they are only estimates, so they cannot guarantee a strength class. A 1:2:4 mix gives about 20-25 N/mm² and roughly matches C20, for foundations, oversite and garage floors without steel. A 1:1.5:3 mix gives about 25 N/mm², and a lean 1:3:6 about 15 N/mm² for oversite and mass fill. Reinforced work needs a designated mix from a supplier: GEN1 suits unreinforced foundations and RC25/30 reinforced ones. A domestic driveway takes PAV1, a paving mix with a typical strength of about 35 N/mm² at 28 days, rather than a site-mixed 1:2:4. For DIY mixing, bagged general purpose ballast, which is sand and aggregate already combined, is the simplest route, so follow the ratio on the bag for the job.
Approved Document A sets minimum depths that catch people out. Strip foundations should go at least 0.45m to their underside to avoid frost, unless they sit on rock. On clay soils the minimum is 0.75m for low shrinkage clay, 0.9m for medium and 1.0m for high, and these depths may need to increase to reach satisfactory ground or where there are trees nearby. Thirsty species such as oak and willow can demand much more, so take advice if one is close. Common guidance on slab thickness is 100mm for a domestic patio, 125mm for a driveway carrying cars, and 150mm or more for vans and heavy use. A142 mesh is standard reinforcement for driveways, with A193 where vehicles load the slab. Any structural foundation work needs a Building Notice or Full Plans, so speak to local Building Control first.
Concrete gains strength slowly rather than all at once. It reaches 70% of its strength at 7 days and 95% at 28 days, the industry standard for testing. Light foot traffic is fine after 24-48 hours, cars after 7 days, and full loading after 28 days. Curing conditions matter more than most people expect, with 10-25°C and 60-90% humidity being ideal. Below 5°C the concrete will not cure properly, so use an accelerator additive or wait for milder weather. Above 30°C it dries too fast and cracks, so mist the surface with water for the first 3 days. Covering the pour with plastic sheeting or wet hessian gives a slower, stronger cure, and in a UK winter it is worth avoiding any pour where the ground temperature is below 5°C.
Project costs put the concrete itself in perspective, here at Checkatrade's August 2026 ready-mix rates and before wastage. A patio of 20 m² at 100mm needs 2 m³, so £200-£320 of ready-mix and £100-£200 of delivery sit alongside £150 of base materials such as Type 1 sub-base and weed membrane, plus £500-£800 of labour if you hire it, giving £950-£1,470 in total. A driveway of 50 m² at 125mm takes 6.25 m³, so £625-£1,000 of concrete, £100-£200 of delivery (more if it takes a second load), £400 of base, £150 of edging and £1,500-£2,500 of labour, so £2,775-£4,250 overall. A shed base of 3m × 2m at 100mm needs 0.6 m³, or 0.66 m³ with 10% wastage. That is 66 bags of 20 kg, about £740 at the £11.20 Wickes charged for a single bag in November 2026, plus the work of mixing them, so ready-mix usually wins. Bags only beat a £500 minimum order below about 45 bags, or 0.45 m³.
Example: Garden shed base, 3 m × 2.4 m × 0.1 m deep
- Volume: 3 × 2.4 × 0.1 = 0.72 m³
- Add 10% wastage: 0.72 × 1.10 = 0.79 m³
- Bags: 0.79 ÷ 0.0125 ≈ 64 of 25 kg, or 0.79 ÷ 0.01 ≈ 80 of 20 kg
- Or order ready-mix, checking the supplier's minimum order first
Frequently Asked Questions
- How do I work out how much concrete a slab needs?
- For a rectangular slab, multiply length by width by depth. For round post holes, use pi times the radius squared times depth. The result in cubic metres tells you how much ready-mix to order. A 20 kg bag of ready-to-use concrete makes about 0.01 cubic metres, and the calculator applies the same rate to a 25 kg bag, so 0.0125. Add 5-10% on top for wastage, spillage and uneven ground before you place the order.
- Should I use bags or order ready-mix concrete?
- Bags suit small jobs and ready-mix suits the rest. Checkatrade's August 2026 guide puts ready-mix at £100-£160 per cubic metre plus £100-£200 for delivery, with a minimum order of about £500 and possibly a part-load fee. A 20 kg bag makes about 0.01 cubic metres and cost £11.20 at Wickes in November 2026, so bags only beat a £500 minimum order below about 45 bags, or 0.45 m³. A shed base needing 0.6 m³ takes about 66 bags with 10% wastage, around £740, so ready-mix usually wins there.
- Which concrete mix should I use for a driveway?
- PAV1, the paving mix for domestic driveways, with a typical strength of about 35 N/mm² at 28 days. Ask a ready-mix supplier for it by name rather than mixing on site. A 1:2:4 mix by volume roughly matches C20 and suits foundations, oversite and garage floors without steel, while GEN1 suits unreinforced foundations and RC25/30 reinforced ones. Volume ratios are only estimates, so reinforced work needs a designated mix.
- How long does concrete take to cure properly?
- Concrete reaches 70% of its strength at 7 days and 95% at 28 days, which is the point used for testing. You can walk on it after 24-48 hours, drive a car on it after 7 days, and load it fully after 28 days. Ideal conditions are 10-25°C with 60-90% humidity. Below 5°C it will not cure properly, so use an accelerator or wait, and above 30°C mist the surface with water for the first 3 days to stop it cracking.
- Do I need mesh reinforcement in a concrete slab?
- Slabs larger than 4m², or any slab that will carry weight, should have A142 or A193 steel mesh, which weigh 2.22kg and 3.02kg per square metre. A142 is the standard choice for driveways and A193 suits areas taking vehicle loads. Lift the mesh clear of the base rather than resting it there. Keep the finished pour moist for 7 days or more under polythene or wet hessian while it hardens.